Johnson Street Condominiums
Project Summary
Mobilization
• Charter will utilize SW Tranquility Terrace for staging Charter’s mobile office, disposal bins, material storage, portable restrooms and other staging needs.
Access and Weather Protection
• Pump Jacks and Ladders will be utilized to perform the exterior scope of repairs.
• Existing WRB components and/or plastic Visqueen will be used as necessary to weather protect the
areas being worked on.
Siding, Windows, Sliding Glass Doors, and Entry Doors.
• Targeted lap siding, weather resistive barrier (WRB), flashings, trim and wall sheathing will be removed
and replaced as indicated on the construction drawings.
• All panel siding will be removed and replaced with lap siding as indicated on the construction drawings.
• All penetrations (lights, outlets, vents, pipes, etc.) will be flashed and waterproofed.
• Windows and sliding glass doors will be removed and replaced with new.
• Entry swing doors will be flashed in place.
Roofs and Attics
• Full removal and replacement of the roofs.
• Tightlining in all attics.
• New 3×4” Flat Downspouts will be installed at the same locations as existing downspouts.
Decks
• Elevated Decks will be inspected, prepped to receive a recoat.
• Railings will be removed and reinstalled in their existing condition.
Interior Repairs
• Drywall repairs related to the construction project will be repaired to the original state prior to starting the
repairs and painted and textured to match as closely as possible.
• Interior finishes may need to be cut back to accommodate the installation of the new windows and
sliding glass doors.
• Charter will need to conduct a unit walk-through / inspection on the interior of each unit prior to starting
work on the interior to verify existing conditions of all units and audit the size and condition of the
existing windows and sliding glass doors.
Exterior Painting
• New exterior paint on all buildings.
Electrical
• Removal and replacement of exterior lights and outlets will be installed on mounting blocks to facilitate envelope remediation in applicable locations. 9
Project Summary
Johnson Street Condominiums
Building Envelope Rehabilitation Project
Estimated Project Duration: 5 months
I am text block. Click edit button to change this text. Lorem ipsum dolor sit amet, consectetur adipiscing elit. Ut elit tellus, luctus nec ullamcorper mattis, pulvinar dapibus leo.
I am text block. Click edit button to change this text. Lorem ipsum dolor sit amet, consectetur adipiscing elit. Ut elit tellus, luctus nec ullamcorper mattis, pulvinar dapibus leo.
My name is Lisa Foster, Homeowner Liaison with Charter Construction. It is my pleasure to be your communications resource for all information during the construction project.
My role is to make the construction process less stressful for you through frequent and open communication. I will be available to answer your ongoing questions and address your concerns as they arise. I will provide weekly updates, indicating the planned progression of scheduled work for the coming week, and offer information regarding when and how the construction will directly impact you.
Please feel free to contact me at any time with questions, concerns, suggestions or complaints. I will respond to your calls and correspondence promptly. I can be reached through this website during business hours (see the Feedback page), via email or by phone at the numbers below. I look forward to getting to know you.
Office 503-546-2600
Cell 503-318-2373
[email protected]
Weekly Updates
05/15/26 - 05/22/26
Projected work for the week of May 15th – May 22nd:
*Construction schedules are subject to change*
**Crews will not be working on Monday, 05/25/26, in observance of Memorial Day**
Work done the week of 05/18/26:
• Job mobilization started including set up of job site office, portable toilets, and equipment.
• Storage containers were delivered onsite.
• Installation of temporary power for Buildings 1 and 3 was completed.
• Demolition of siding and trim at Building 5 started.
Work to be done the week of 05/26/26:
• Demolition of siding and trim at Building 5 to continue.
• Electrical disconnects at Building 5 soffits and walls to start.
Resident Reminders:
• The Weekly Update is meant to be a broad overview of our contractual repair work and is not inclusive of all work done, or to be done, in the current or upcoming weeks. Our construction schedule is subject to change pending unforeseen conditions, scope of work revisions, weather delays, etc.
• Please do not approach crews to discuss construction concerns or issues. You will need to contact your Homeowner Liaison, Lisa Foster at [email protected] or 503.546.2600, for more information. If after-hours, you may request to have Lisa Foster or Richard Sample paged.
Safety:
• If you notice anyone on the construction equipment or scaffolding after 6:00pm other than Richard Sample, please call 911 immediately.
• Material Safety Data Sheets are available upon request in our job site office.
• **For any construction related emergency, please call your Homeowner Liaison Lisa Foster at 503.546.2600, including after-hours, and request to have Lisa paged.
• Please note that we have a 24-Hour Emergency Response Team for any earthquake, water, fire/wind board ups, and insurance claim emergencies, which may not be project related and can be called for assistance at 503.546.2600.
06/22/26 - 06/29/26
Projected work for the week of June 22nd – June 26th:
*Construction schedules are subject to change*
Work done the week of 06/15/26:
• Demolition of siding and trim at Building 2 was started.
• Demolition of paper and damaged OSB plywood on Building 4 started.
• Demolition of paper and damaged OSB plywood at Building 5 continued.
Work to be done the week of 06/22/26:
• Demolition of paper and damaged OSB plywood at Building 5 to continue.
• Installation of new plywood on Building 5 to start.
• Demolition of damaged OSB plywood at Building 4 continued.
• Demolition of siding and trim at Building 1 to start.
Resident Reminders:
• The Weekly Update is meant to be a broad overview of our contractual repair work and is not inclusive of all work done, or to be done, in the current or upcoming weeks. Our construction schedule is subject to change pending unforeseen conditions, scope of work revisions, weather delays, etc.
• Please do not approach crews to discuss construction concerns or issues. You will need to contact your Homeowner Liaison, Lisa Foster at [email protected] or 503.546.2600, for more information. If after-hours, please request to be transferred to Lisa Foster or, you can request to have either Lisa Foster or Richard Sample paged if you are speaking with a live person.
Safety:
• If you notice anyone on the construction equipment or scaffolding after 6:00pm other than Richard Sample, please call 911 immediately.
• Material Safety Data Sheets are available upon request in our job site office.
• **For any construction related emergency, please call your Homeowner Liaison Lisa Foster at 503.546.2600, including after-hours, and request to be transferred to Lisa paged, or, if you are connected to a live person, request to have Lisa Foster or Richard Sample paged.
• Please note that we have a 24-Hour Emergency Response Team for any earthquake, water, fire/wind board ups, and insurance claim emergencies, which may not be project related and can be called for assistance at 503.546.2600.
06/15/26 - 06/19/26
Projected work for the week of June 8th – June 15th:
*Construction schedules are subject to change*
Work done the week of 06/08/26:
• Demolition of siding and trim at Building 3 was completed.
• Delivery of windows took place on the 8th and the 11th.
• Demolition of paper and damaged OSB plywood at Building 5 started.
Work to be done the week of 06/015/26:
• Demolition of paper and damaged OSB plywood at Building 5 to continue.
• Installation of new plywood at Building 5 to start.
• Demolition of damaged OSB plywood at Building 4 to start.
• Demolition of siding and trim at Building 3 to start.
Resident Reminders:
• The Weekly Update is meant to be a broad overview of our contractual repair work and is not inclusive of all work done, or to be done, in the current or upcoming weeks. Our construction schedule is subject to change pending unforeseen conditions, scope of work revisions, weather delays, etc.
• Please do not approach crews to discuss construction concerns or issues. You will need to contact your Homeowner Liaison, Lisa Foster at [email protected] or 503.546.2600, for more information. If after-hours, you may request to have Lisa Foster or Richard Sample paged.
Safety:
• If you notice anyone on the construction equipment or scaffolding after 6:00pm other than Richard Sample, please call 911 immediately.
• Material Safety Data Sheets are available upon request in our job site office.
• **For any construction related emergency, please call your Homeowner Liaison Lisa Foster at 503.546.2600, including after-hours, and request to have Lisa paged, ask to be transferred to Lisa if you do not hear a live person.
• Please note that we have a 24-Hour Emergency Response Team for any earthquake, water, fire/wind board ups, and insurance claim emergencies, which may not be project related and can be called for assistance at 503.546.2600.
06/05/26 - 06/12/26
Projected work for the week of June 5th – June 12th:
*Construction schedules are subject to change*
Work done the week of 06/01/26:
• Demolition of siding and trim at Building 4 is now complete.
Work to be done the week of 06/08/26:
• Window delivery will be on the 8th.
• Demolition of siding and trim on Building 3 to start.
• Electrical disconnects, soffit lighting at Building 3, 4 and 5 to start being removed.
Resident Reminders:
• The Weekly Update is meant to be a broad overview of our contractual repair work and is not inclusive of all work done, or to be done, in the current or upcoming weeks. Our construction schedule is subject to change pending unforeseen conditions, scope of work revisions, weather delays, etc.
• Please do not approach crews to discuss construction concerns or issues. You will need to contact your Homeowner Liaison, Lisa Foster at [email protected] or 503.546.2600, for more information. If after-hours, you may request to have Lisa Foster or Richard Sample paged.
Safety:
• If you notice anyone on the construction equipment or scaffolding after 6:00pm other than Richard Sample, please call 911 immediately.
• Material Safety Data Sheets are available upon request in our job site office.
• **For any construction related emergency, please call your Homeowner Liaison Lisa Foster at 503.546.2600, including after-hours, and request to have Lisa paged, ask to be transferred to Lisa if you do not hear a live person.
• Please note that we have a 24-Hour Emergency Response Team for any earthquake, water, fire/wind board ups, and insurance claim emergencies, which may not be project related and can be called for assistance at 503.546.2600.
06/01/26 - 06/05/26
Projected work for the week of June 1st – June 5th:
*Construction schedules are subject to change*
Work done the week of 05/25/26:
• Demolition of siding and trim at Building 5 is now complete.
• Demolition of siding and trim on Building 4 started.
Work to be done the week of 06/01/26:
• Demolition of siding and trim at Building 4 to continue.
• Demolition of siding and trim on Building 3 to start.
• Electrical disconnects, soffit lighting at Building 3, 4 and 5 to start being removed.
Resident Reminders:
• The Weekly Update is meant to be a broad overview of our contractual repair work and is not inclusive of all work done, or to be done, in the current or upcoming weeks. Our construction schedule is subject to change pending unforeseen conditions, scope of work revisions, weather delays, etc.
• Please do not approach crews to discuss construction concerns or issues. You will need to contact your Homeowner Liaison, Lisa Foster at [email protected] or 503.546.2600, for more information. If after-hours, you may request to have Lisa Foster or Richard Sample paged.
Safety:
• If you notice anyone on the construction equipment or scaffolding after 6:00pm other than Richard Sample, please call 911 immediately.
• Material Safety Data Sheets are available upon request in our job site office.
• **For any construction related emergency, please call your Homeowner Liaison Lisa Foster at 503.546.2600, including after-hours, and request to have Lisa paged, ask to be transferred to Lisa if you do not hear a live person.
• Please note that we have a 24-Hour Emergency Response Team for any earthquake, water, fire/wind board ups, and insurance claim emergencies, which may not be project related and can be called for assistance at 503.546.2600.
07/27/26 - 07/31/26
Projected work for the week of July 27th – July 31st:
*Construction schedules are subject to change*
Work done the week of 07/20/26:
• Installation of sliding glass doors and windows on Buildings 4 and 3 continued and started on Building 2.
• Demolition of Weather Resistive Barrier (WRB) and damaged OSB plywood on Buildings 4 and 3 continued.
• Demolition of dry-rot studs and reframing of new studs for Building 4 continued.
• Demolition of roof shingles and paper on Buildings 5 and 4 has been completed.
• Installation of roofing material for mock-up continued.
• Installation of interior caulking around windows and sliding glass doors at Buildings 4 and 3 has been completed.
Work to be done the week of 07/27/26:
• Demolition of damaged OSB plywood at Building 2 to start.
• Installation of new plywood at Buildings 2 and 3 to continue.
• Installation of windows and sliding glass doors at Buildings 4 and 2 to continue.
• Installation of interior caulking around windows and sliding glass doors at Buildings 3 and 2 to continue.
• Demolition of roof shingles at Buildings 4 and 3 to be completed.
• Installation of new shingles at Buildings 5 and 4 to start.
Resident Reminders:
• The Weekly Update is meant to be a broad overview of our contractual repair work and is not inclusive of all work done, or to be done, in the current or upcoming weeks. Our construction schedule is subject to change pending unforeseen conditions, scope of work revisions, weather delays, etc.
• Please do not approach crews to discuss construction concerns or issues. You will need to contact your Homeowner Liaison, Lisa Foster at [email protected] or 503.546.2600, for more information. If after-hours, please request to be transferred to Lisa Foster or, you can request to have either Lisa Foster or Richard Sample paged if you are speaking with a live person.
Safety:
• If you notice anyone on the construction equipment or scaffolding after 6:00pm other than Richard Sample, please call 911 immediately.
• Material Safety Data Sheets are available upon request in our job site office.
• **For any construction related emergency, please call your Homeowner Liaison Lisa Foster at 503.546.2600, including after-hours, and request to be transferred to Lisa or, if you are connected to a live person, request to have Lisa Foster or Richard Sample paged.
• Please note that we have a 24-Hour Emergency Response Team for any earthquake, water, fire/wind board ups, and insurance claim emergencies, which may not be project related and can be called for assistance at 503.546.2600.
07/20/26 - 07/27/26
Projected work for the week of July 20th – July 27th:
*Construction schedules are subject to change*
Work done the week of 07/13/26:
• Installation of sliding glass doors and windows on Buildings 4 and 3 continued.
• Demolition of Weather Resistive Barrier (WRB) and damaged OSB plywood on Buildings 4 and 3 continued.
• Demolition of dry-rot studs and reframing of new studs for Building 4 started.
• Demolition of roof shingles and paper on Buildings 5 and 4 started.
• Installation of roofing material for mock-up started.
• Installation of interior caulking around windows and sliding glass doors at Buildings 4 and 3 continued.
Work to be done the week of 07/20/26:
• Demolition of damaged OSB plywood at Building 2 to start.
• Installation of new plywood at Buildings 3 and 4 to continue.
• Installation of windows and sliding glass doors at Buildings 3 and 2 to continue.
• Installation of interior caulking around windows and sliding glass doors at Building 3 and 2 to start and continue.
• Demolition of roof shingles at Building 4 to continue and at Building 3 to start.
• Installation of new shingles at Buildings 5 and 4 to start.
Resident Reminders:
• The Weekly Update is meant to be a broad overview of our contractual repair work and is not inclusive of all work done, or to be done, in the current or upcoming weeks. Our construction schedule is subject to change pending unforeseen conditions, scope of work revisions, weather delays, etc.
• Please do not approach crews to discuss construction concerns or issues. You will need to contact your Homeowner Liaison, Lisa Foster at [email protected] or 503.546.2600, for more information. If after-hours, please request to be transferred to Lisa Foster or, you can request to have either Lisa Foster or Richard Sample paged if you are speaking with a live person.
Safety:
• If you notice anyone on the construction equipment or scaffolding after 6:00pm other than Richard Sample, please call 911 immediately.
• Material Safety Data Sheets are available upon request in our job site office.
• **For any construction related emergency, please call your Homeowner Liaison Lisa Foster at 503.546.2600, including after-hours, and request to be transferred to Lisa or, if you are connected to a live person, request to have Lisa Foster or Richard Sample paged.
• Please note that we have a 24-Hour Emergency Response Team for any earthquake, water, fire/wind board ups, and insurance claim emergencies, which may not be project related and can be called for assistance at 503.546.2600.
07/13/26 - 07/17/26
Projected work for the week of July 13th – July 17th:
*Construction schedules are subject to change*
Work done the week of 07/06/26:
• Installation of sliding glass doors and windows on Buildings 5 and 4 started.
• Demolition of Weather Resistive Barrier (WRB) and damaged OSB plywood on Buildings 5 and 4 continued.
• Installation of windows and sliding glass doors for mock-ups are completed.
• Installation of interior caulking around windows and sliding glass doors at Building 5 continued.
Work to be done the week of 07/13/26:
• Demolition of damaged OSB plywood at Buildings 3 and 4 to continue.
• Installation of new plywood at Buildings 3 and 4 to continue.
• Installation of windows and sliding glass doors at Buildings 3 and 4 to continue.
• Installation of interior caulking around windows and sliding glass doors at Building 4 to start.
• Demolition of roof shingles at Building 5 to start.
Resident Reminders:
• The Weekly Update is meant to be a broad overview of our contractual repair work and is not inclusive of all work done, or to be done, in the current or upcoming weeks. Our construction schedule is subject to change pending unforeseen conditions, scope of work revisions, weather delays, etc.
• Please do not approach crews to discuss construction concerns or issues. You will need to contact your Homeowner Liaison, Lisa Foster at [email protected] or 503.546.2600, for more information. If after-hours, please request to be transferred to Lisa Foster or, you can request to have either Lisa Foster or Richard Sample paged if you are speaking with a live person.
Safety:
• If you notice anyone on the construction equipment or scaffolding after 6:00pm other than Richard Sample, please call 911 immediately.
• Material Safety Data Sheets are available upon request in our job site office.
• **For any construction related emergency, please call your Homeowner Liaison Lisa Foster at 503.546.2600, including after-hours, and request to be transferred to Lisa or, if you are connected to a live person, request to have Lisa Foster or Richard Sample paged.
• Please note that we have a 24-Hour Emergency Response Team for any earthquake, water, fire/wind board ups, and insurance claim emergencies, which may not be project related and can be called for assistance at 503.546.2600.
06/29/26 - 07/06/26
Toggle content go
Projected work for the week of June 29th – July6th:
*Construction schedules are subject to change*
**Crews will not be working onsite Friday, 07/03/26, in observance of the July 4th Holiday**
Work done the week of 06/29/26:
• Demolition of siding and trim at Building 1 was completed.
• Demolition of Weather Resistive Barrier (WRB) and damaged OSB plywood on Building 5 continued.
• Installation of windows and SGD for mock-ups started.
• Installation of interior caulking around windows and sliding glass doors was performed.
Work to be done the week of 07/06/26:
• Demolition of damaged OSB plywood at Buildings 3, 4, and 5 to continue.
• Installation of new plywood on Buildings 3, 4, and 5 to continue.
• Installation of windows and sliding glass doors on Building 5 to continue.
• Installation of interior caulking around windows and sliding glass doors to continue.
Resident Reminders:
• The Weekly Update is meant to be a broad overview of our contractual repair work and is not inclusive of all work done, or to be done, in the current or upcoming weeks. Our construction schedule is subject to change pending unforeseen conditions, scope of work revisions, weather delays, etc.
• Please do not approach crews to discuss construction concerns or issues. You will need to contact your Homeowner Liaison, Lisa Foster at [email protected] or 503.546.2600, for more information. If after-hours, please request to be transferred to Lisa Foster or, you can request to have either Lisa Foster or Richard Sample paged if you are speaking with a live person.
Safety:
• If you notice anyone on the construction equipment or scaffolding after 6:00pm other than Richard Sample, please call 911 immediately.
• Material Safety Data Sheets are available upon request in our job site office.
• **For any construction related emergency, please call your Homeowner Liaison Lisa Foster at 503.546.2600, including after-hours, and request to be transferred to Lisa or, if you are connected to a live person, request to have Lisa Foster or Richard Sample paged.
• Please note that we have a 24-Hour Emergency Response Team for any earthquake, water, fire/wind board ups, and insurance claim emergencies, which may not be project related and can be called for assistance at 503.546.2600.
es here, click edit button to change this text.
08/03/26 - 08/07/26
Projected work for the week of August 3rd – August 7th:
*Construction schedules are subject to change*
Work done the week of 07/27/26:
• Installation of sliding glass doors and windows at Buildings 1 and 2 continued.
• Demolition of Weather Resistive Barrier (WRB) and damaged OSB plywood at Buildings 4 and 3 continued.
• Demolition of dry-rot studs and reframing of new studs at Building 4 was completed.
• Demolition of roof shingles and paper at Buildings 1 and 2 was completed.
• Installation of roofing material for mock-up was completed.
• Installation of interior caulking around windows and sliding glass doors at Buildings 1 and 2 continued.
Work to be done the week of 08/03/26:
• Demolition of damaged OSB plywood at Buildings 1 and 2 to continue.
• Installation of new plywood at all Buildings continue.
• Installation of windows and sliding glass doors at Building 1 to be completed.
• Installation of interior caulking around windows and sliding glass doors at Buildings 1 and 2 to be completed.
• Interior caulking punch work to be completed.
• Installation of new shingles at Buildings 4 and 5 to start.
• Inspecting and tight lining duct work in attics to start.
• Installation of new Weather Resistant Barrier (WRB) paper at Building 5 to start.
Resident Reminders:
• The Weekly Update is meant to be a broad overview of our contractual repair work and is not inclusive of all work done, or to be done, in the current or upcoming weeks. Our construction schedule is subject to change pending unforeseen conditions, scope of work revisions, weather delays, etc.
• Please do not approach crews to discuss construction concerns or issues. You will need to contact your Homeowner Liaison, Lisa Foster at [email protected] or 503.546.2600, for more information. If after-hours, please request to be transferred to Lisa Foster or, you can request to have either Lisa Foster or Richard Sample paged if you are speaking with a live person.
Safety:
• If you notice anyone on the construction equipment or scaffolding after 6:00pm other than Richard Sample, please call 911 immediately.
• Material Safety Data Sheets are available upon request in our job site office.
• **For any construction related emergency, please call your Homeowner Liaison Lisa Foster at 503.546.2600, including after-hours, and request to be transferred to Lisa or, if you are connected to a live person, request to have Lisa Foster or Richard Sample paged.
• Please note that we have a 24-Hour Emergency Response Team for any earthquake, water, fire/wind board ups, and insurance claim emergencies, which may not be project related and can be called for assistance at 503.546.2600.
Notices
Johnson Street Condominiums
Building Envelope Rehabilitation Project General Notice
Work Hours: 7:30am – 4:30pm, Mon – Fri
Posted 07/24/26
Building 1: All Units (17261, 17267, 17273)
Crews will be starting the roof demolition on Tuesday, 07/28/26. Please remove all personal items on decks, patios, and walkways to prevent any damages from occurring.
Roof Demolition:
• Crews will begin the roof demolition on Tuesday, 07/28/26.
• Crews will be removing and reinstalling exterior lighting as needed at areas of repairs.
• Plastic sheeting will be applied in areas where necessary for weather protection should it be necessary.
• PLEASE NOTE: Be prepared for noise while this process is taking place.
• Please keep all doors and windows closed during working hours.
• Interior Access will not be needed at this time.
Resident Reminders:
• Driveways will be needed by crew members during working hours.
• Remove all personal items including satellite dishes, and connecting cables, patio furniture, all patios, and at front entryways. BBQ’s, potted plants, and any other personal items must be removed away from construction related areas to avoid possible damage including away from buildings being worked on.
• It is recommended that you remove any fragile items or artwork on the interior walls to avoid possible damage.
• Removal and reinstallation of all owner added hardscape items such as pavers, shed roofs not originally built during construction etc., are the responsibility of the unit owner to remove.
• Charter takes no responsibility for damage to personal items not moved by the homeowner prior to the beginning of repair work.
• Please do not address work crews with construction questions. You must contact the Homeowner Liaison, Lisa Foster, at 503.546.2600 for current information.
• Please secure children and pets at this time.
Safety Reminders:
• For your safety and protection, please use caution around all crews, construction equipment, materials, etc.
• If you notice anyone on the construction equipment after 5:00pm other than Richard Sample, please call 911 immediately.
•
503.546.2600, including after-hours, and request to have Lisa or Richard paged.
• Please note that we have a 24-Hour Emergency Response Team for any earthquake, water, fire/wind board ups, and insurance claim emergencies, which may not be project related and can be called for assistance at 503.546.2600.
Building 3: Unit 2840
Crews will need interior access on Wednesday, 06/10/26, between 8:00am and 4:00pm to remove and re-install a window and sliding glass door for our mock-up procedure. PLEASE NOTE: Your window blinds or curtain including brackets, will need to be removed away from work areas, including any personal items.
Removal and Re-installation of Window and Sliding Glass Door:
• Crews will be removing and re-installing a window and sliding reinstalling for our mock-up on Wednesday, 06/10/26.
• Window openings will be re-secured prior to the completion of daily work.
• Please do not touch window sealant or other materials installed during this process.
• Entry will be between the hours of 8:00am and 12:00pm.
Resident Reminders:
• Please provide at least 3 feet of clearance on the interior of the window and sliding glass door for crews to have clear access.
• Remove art décor and fragile items on or near construction that may fall and break due to vibrations on walls.
• Charter takes no responsibility for damage to personal items, etc. not removed and stored away from construction areas of work by unit owner or resident per instructions above.
• Please secure children and animals away from crews at this time.
• Please do not address work crews with construction questions. For questions or concerns, please call the Homeowner Liaison Lisa Foster, at 503.546.2600.
Safety Reminders:
• For your safety and protection, please use caution around all crews, construction equipment, materials, etc.
• If there is a construction related emergency, please call Lisa Foster at 503.546.2600. Please note that we have a 24-Hour Emergency Response Team for any earthquake, water, fire/wind board ups and insurance claim emergencies, which are not project related. For any after-hour emergency, please call: 503.546.2600.
Schedule
FAQ
I am text block. Click edit button to change this text. Lorem ipsum dolor sit amet, consectetur adipiscing elit. Ut elit tellus, luctus nec ullamcorper mattis, pulvinar dapibus leo.
I am text block. Click edit button to change this text. Lorem ipsum dolor sit amet, consectetur adipiscing elit. Ut elit tellus, luctus nec ullamcorper mattis, pulvinar dapibus leo.
I am text block. Click edit button to change this text. Lorem ipsum dolor sit amet, consectetur adipiscing elit. Ut elit tellus, luctus nec ullamcorper mattis, pulvinar dapibus leo.
I am text block. Click edit button to change this text. Lorem ipsum dolor sit amet, consectetur adipiscing elit. Ut elit tellus, luctus nec ullamcorper mattis, pulvinar dapibus leo.
I am text block. Click edit button to change this text. Lorem ipsum dolor sit amet, consectetur adipiscing elit. Ut elit tellus, luctus nec ullamcorper mattis, pulvinar dapibus leo.
I am text block. Click edit button to change this text. Lorem ipsum dolor sit amet, consectetur adipiscing elit. Ut elit tellus, luctus nec ullamcorper mattis, pulvinar dapibus leo.
I am text block. Click edit button to change this text. Lorem ipsum dolor sit amet, consectetur adipiscing elit. Ut elit tellus, luctus nec ullamcorper mattis, pulvinar dapibus leo.
I am text block. Click edit button to change this text. Lorem ipsum dolor sit amet, consectetur adipiscing elit. Ut elit tellus, luctus nec ullamcorper mattis, pulvinar dapibus leo.
Safety Plan
Charter does whatever it takes to make certain your job site will be as safe and secure as possible. We do so for the benefit of the homeowners, residents, visitors, subcontractors, and employees of our company.
Because we place such a high priority on security and safety, Charter has had an excellent record of accomplishment for many years. We have maintained this record by evaluating each
site carefully, developing a strong plan suited for the location, scope of work, and proactively managing all aspects of work for the duration of the job. The following is our safety information
for owners and residents of the Johnson Street Condominiums.
CONSTRUCTION SITE
1. Safety Meetings – Monday mornings @ 8:00am, in front of the Charter’s site office.
• Our Superintendent Richard Sample will hold safety meetings weekly on the job site.
Discussions will include the necessary precautions and work methods that safeguard the
site for residents and crews.
2. Swing Stages –
• Swing Stages will be used on the exterior of the building while it is being resided.
• Weekly Safety Inspections will be done for all swing stage equipment.
• All swing stages will be closed off during non-working hours.
3. Power Tools, Utility Cords & Equipment –
• Charter’s storage area
container. The storage area container will be secured at the end of each workday.
4. Construction Site –
• A construction (jobsite) office will be on site in a location marked with signage.
• The site is to be kept as free of debris as much as possible during the course of the workday and cleaned up at the end of each workday.
• Materials and supplies are to remain organized and stored when not in use.
• The Superintendent and Charter’s crew will know the locations of all gas shut-off valves, electrical main panels, and building water main lines.
• Emergency numbers for all utility companies will be readily available in the site office.
12
Site Safety Plan
Johnson Street Condominiums
Building Envelope Rehabilitation Project
5. Obey all Pedestrian Routing Signage –
• Signage will be posted in designated areas to keep residents and pets clear of danger whenever applicable.
• Locations marked with Red danger tape: do not pass through at any time.
• Locations marked with Yellow caution tape: Ask the crew if you can safely pass
through before entering the area.
6. Stay alert to construction equipment and ongoing construction activities.
• Watch for construction workers, moving equipment, swing stages jacks and ladders,
boom lifts, etc.
• Material and construction equipment may occasionally obstruct views when in use.
SECURITY PRECAUTIONS
1. Construction Crew Identity –
• All members of the Charter construction crew wear articles of clothing with Charter logos.
• Subcontractor crews are encouraged to wear apparel that identifies their company.
• All members of the Charter construction crew as well as subcontractors must wear
high-visibility vests and/or shirts (bright orange, yellow or green).
• Charter crews may question any person on the site who is unfamiliar to them. Our
crew will request their identity and ask why they are in the construction area.
2. Materials Storage –
• Tools, materials, etc. will be secured in an onsite location. Material Safety Data
Sheets (SDS) will be filed at the site office.
• The storage area will remain locked outside of business hours.
13
Photos
Have a question? I’m here to help.
Lisa Foster
Office 503-546-2600
Cell 503-318-2373
[email protected]